Nebius plans $40B buildout on prepayments and loans

By

Published

Reporting from TechCrunch

Nebius guides to $40 to $45 billion of 2027 capex, which it expects to fund mostly from customer prepayments and contract-backed loans.

What it means for founders

  • Nebius GPU hours cost more. Nebius says Q3 prices rose an average of over 20% per GPU-hour from Q2. Its reserve auctions settled more than 15% above the reserve price, and short-term clusters sell at more than double the reserved rate. If you rent Nebius's three to six month clusters, budget for that premium.
  • Bring cash to the table. A startup negotiating a dedicated Nebius cluster may be asked for a prepayment that ties up runway before the GPUs arrive.
  • Ask which building you land in. Nebius says its delays came from sites it does not control. Before signing with any neocloud, ask whether your cluster sits in an owned or leased site, what delivery date is guaranteed, and what you get if it slips. The same diligence applies to other neoclouds now raising capital.
  • Watch the Q2 2027 tranches. Separate from its spending plan, Nebius says it can borrow against over $40 billion in comparable committed revenue. An early test of that model is whether Microsoft accepts the new dates.

What we don't know yet

Nebius has not said if Microsoft accepted the revised schedule, TechCrunch notes, and Microsoft has cancelled nothing in public. Nebius also gave no debt and equity split for the 2027 budget.

The story

On November 12 Nebius told shareholders it expects $40 to $45 billion of capital spending in 2027. It expects customer prepayments and loans secured against its investment-grade contracts to fund 75% to 85% of that bill. Meanwhile a New Jersey site serving Microsoft runs months late. Nebius stock closed 17% lower, TechCrunch reports.

How Nebius wants to pay for it

In its Q3 2026 shareholder letter, Nebius calls prepayment the standard structure for its deals. It expects $10 billion in committed prepayments this year and $17 to $20 billion in 2027. Nebius says prepayments on third-quarter deals of a year or longer topped 100% of the capex behind them, against 50% to 60% in Q2.

Contract-backed debt does the other part. In July Nebius closed a $775 million facility at SOFR plus 2.50%, and says its Microsoft and Meta contracts qualify too. It ended September holding $7.4 billion of cash.

Quarterly revenue came to $980.8 million, up 571%, though roughly $325 million was a one-off. Nebius now sees 2026 sales landing at the low end of its $3.0 to $3.4 billion range and guides to $12 to $13 billion for 2027.

The Microsoft problem

DataOne, which operates the Vineland, New Jersey site, began retiring part of its temporary generation in late Q3, ahead of a move to Bloom Energy fuel cells, a decision Nebius says reset the schedule. TechCrunch reports the switch was not entirely by choice: New Jersey regulators imposed a $1.1 million fine on the DataOne facility over gas generators it ran without permits. Nebius expects to deliver more than half the Microsoft capacity by year end, with the rest slipping to Q2 2027. "Building at this scale is hard, and delays are part of our industry right now," Arkady Volozh, the CEO, said, per TechCrunch.

TechCrunch, citing Nebius's own summary of the deal, says Microsoft can cut off the delayed capacity once a grace period runs out if no substitute is offered, and that lateness triggers penalties. Citing Bloomberg, it reports that Microsoft is tightening oversight of third-party projects, including those of Nebius, IREN and Nscale. Nebius says Microsoft has been involved in the planning and that its own sites are on schedule or early. TechCrunch says it sought comment from all three companies.