Texas restarts data center permits weeks before Hinojosa takes office

Abbott's office ended the pause on environmental permits. The grid queue of 1,800 projects is a separate gate, and its audit is not public yet.
What it means for founders
Most founders rent compute rather than build it. Three things follow.
Read the restart narrowly. Environmental permits are moving. Grid connections for large loads still wait on ERCOT's report and the Batch Zero study behind it, which ERCOT's Chad Seely said in August would not be finished by its 9 April 2027 deadline, Utility Dive reported. If a provider quotes Texas capacity arriving in 2027, ask whether the site has approval to energize or only a permit.
Watch on-site gas. All three plants Public Citizen lists exist to power data centers directly. Own generation sidesteps part of the grid queue but needs a TCEQ air permit, the gate that just reopened. Enki expects more of these filings before 19 January.
Price in the politics. Hinojosa said in an October video that as governor she would ban data center approvals until the Legislature passes laws to protect Texans, the Texas Tribune reported in a story KSAT republished. Her party won the state House but not the Senate, Data Center Frontier reports, and nobody has said how her moratorium would treat permits already issued. If you are signing a multi-year compute contract tied to a Texas campus, ask for delivery dates backed by approvals in hand, and an exit if a state pause delays them. The federal side of the siting fight is in Enki's story on Trump's threatened tax on US data centers built abroad.
What we don't know yet
ERCOT has published no findings, and nothing public says whether any Batch Zero project has been cleared to connect. Public Citizen cites a report that ERCOT said it was still working to complete the audit, which sits awkwardly with the governor's notice. Nothing Enki read counts applications filed since 13 November, so the reported rush has no number.
The story
Texas has restarted environmental permits for data centers. On 13 November, Governor Greg Abbott's office told the Texas Commission on Environmental Quality (TCEQ) that the grid operator, ERCOT, "has completed the community impact review", CBS Austin reported. TCEQ says it "has resumed its normal permit review process." Abbott leaves office on 19 January. Gina Hinojosa, the Democrat who beat him on 3 November, has promised a moratorium on data center approvals.
Tom's Hardware, citing a business paper's reporting, says that builders are rushing for approvals before she arrives, and frames the move as lifting a freeze on more than 1,800 projects. Texas shut two separate gates this year, and only one has visibly reopened. For a founder renting compute in Texas, the difference decides whether new capacity is months or years away.
Two pauses, and only one restart
The first gate is the grid. On 3 August Abbott ordered ERCOT and the state's utility regulator to audit every data center in ERCOT's interconnection process before any could move forward. His release put requests at about 474 gigawatts, more than five times the state's record peak demand, roughly 90% of them data centers. The 1,800 figure is the whole queue, Inside Climate News reported. The audit targets about 300 projects in Batch Zero, ERCOT's first study group for loads of 75 MW and above.
The second gate is environmental. On 21 September Abbott told TCEQ to "halt all permits sought by data centers" pending the audit. That reaches air and water permits, law firm DLA Piper noted.
Only the second gate is known to have reopened. Utility Dive reported in August that the audit must finish before those studies continue and grid connections resume. The El Paso Times reports that both the audit and a community impact report covering 433 projects go to the utility commission on 10 December, for discussion on 17 December.
The restart left almost no public record
Enki checked the governor's news page on 27 November. No November release headline mentions data centers, TCEQ or ERCOT. The 13 November notice reached the public through TCEQ statements to reporters, and it stated no findings, CBS Austin reports.
Approvals came quickly. Public Citizen, an advocacy group that monitors TCEQ, says the agency approved air permits for three data center gas plants on 16 November, 3,500 MW between them, through a standard permit route with no public notice. Such permits are not unusual below the emissions limits that trigger fuller review, the El Paso Times notes. The plants are SpaceX's Boca Chica plant, the CloudBurst plant near San Marcos and Atlas Energy Solutions' plant in Shackelford County. It says 17 construction approvals suspended in October were active again by 13 November. These are Public Citizen's figures; Enki has not seen TCEQ's records.
Enki's read: "U-turn" overstates it. Abbott tied the permit pause to ERCOT finishing its audit, and his office now says the information gathering is done. What stands out is the timing: permits restarted four weeks before the findings are due. CBS Austin said it had asked the governor's office for comment and was awaiting a reply.
Demand never paused. Data Center Frontier reports that Riot Platforms signed a 910 MW, 15-year lease at its Corsicana campus, which Riot estimates is worth about $28 billion over its initial term, and that Riot's quarterly filing names Anthropic as the tenant, with delivery in three phases through July 2028. More on that tenant is in Enki's Anthropic coverage.
Sources
Reporting
More in Policy & Safety
- OpenAI countersues Apple, says it pressured suppliers and set a 'trap' for staffOpenAI's counterclaims say Apple took its secrets and leaned on shared suppliers. What it means for anyone hiring from Apple or building hardware.Techmeme · 12h ago
- Amazon bars more than 60 AI agents by name, OpenAI's and Google's among themAgents from OpenAI, Meta, Google and Instinct promise to shop for you. Enki checked Amazon's rules: they name and bar more than 60 AI agents.CNBC Technology · 15h ago

- Nvidia partner lists include two Chinese-owned US firms, CBS findsRiCloud AI and Aivres sit on Nvidia's partner lists with Chinese parents. Filings show how little a partner badge tells a GPU buyer.SiliconANGLE AI · 1d ago

- Nvidia reportedly halts server shipments to four Southeast Asian countriesA new US rule puts licences on AI chips bound for Singapore, Malaysia, Indonesia and Thailand. Thousands of B300s are now looking for buyers, CNBC reports.The Decoder · 1d ago

- FCC clears SpaceX's Starmind for up to 1 million data center satellitesThe FCC licence covers backup radio links, not compute. SpaceX has until 2033 to fly one satellite, and no debris plan above 600 km is approved yet.The Decoder · 1d ago